Custom Residential Electrical & BIM Design

Personal Project · June 2025 – July 2026

A two-storey house developed from dimensioned 2D AutoCAD plans into a 3D Revit/BIM model, then extended with residential lighting and power plans, branch circuits, a panel schedule, basic load calculations, and a simplified single-line diagram.

  • AutoCAD
  • Autodesk Revit
  • BIM
  • Residential Electrical Design
2 storeysresidential design
2025–2026self-directed project timeline
2D → 3DAutoCAD drawings to Revit/BIM model
Lighting + powerplans for both floors

Project Overview

The Custom 2-Storey Residential Electrical & BIM Design was a long-term personal project I completed to develop practical experience with architectural drafting, BIM modeling, and residential electrical-system design.

I began by developing the house as a complete 2D AutoCAD drawing package, including detailed first- and second-floor plans and dimensions. I then recreated the same house as a 3D Autodesk Revit model, building it from the foundation through the roof and adding architectural elements, furniture, materials, and finishes.

Rather than stopping with the architectural model, I expanded the project into an electrical and BIM design exercise. I developed residential lighting and power plans, placed electrical devices throughout the building, organized loads into branch circuits, documented circuit assignments, and considered how the electrical system interacted with the architectural design.

The overall workflow became:

2D Architectural DesignAutoCAD Drawings3D Revit/BIM ModelElectrical LayoutCircuit OrganizationElectrical DocumentationBIM Coordination

This project helped me understand that an electrical design is not developed separately from a building. The electrical system has to be designed around how the building is actually laid out and used.

1. Architectural Design & AutoCAD Drafting

The first stage was developing the complete house in AutoCAD.

I created detailed first- and second-floor plans containing the building geometry, rooms, walls, doors, windows, stairs, bathrooms, kitchen, bedrooms, living spaces, garage, and other architectural features.

I also dimensioned the floor plans so that the drawing communicated the physical size and location of the different building elements.

This stage was important because a floor plan is not simply supposed to look like a house.

A technical drawing has to communicate:

  • where something is
  • how large it is
  • how it relates spatially to other components
  • how another person should interpret the design

I therefore focused on maintaining organized dimensions, consistent drafting, readable plans, and standardized technical presentation.

My drafting was guided by residential-design expectations, Ontario Building Code guidance, and accepted National CADD drafting practices.

2. Why Dimensioning Was Important

Dimensioning was one of the areas where this project significantly improved my attention to detail.

A CAD model may visually show where a wall or room is located, but someone looking at a technical drawing needs actual measurements to understand the design.

The dimensioned plans therefore communicate things such as overall building dimensions and the relative locations and sizes of rooms, walls, openings, and architectural features.

This forced me to think beyond simply drawing geometry.

I had to ask:

Could somebody else understand the design from the drawing without having created the model themselves?

That changed how I thought about CAD. It became less about drawing and more about technical communication.

3. Transition from AutoCAD to Revit

Once the 2D architectural design was established, I recreated the same house in Autodesk Revit.

This represented an important change in workflow.

In AutoCAD, I was primarily working with 2D drafting geometry.

In Revit, I was creating actual building elements within a coordinated BIM model.

Instead of simply drawing parallel lines representing a wall, for example, the Revit model treats the wall as an architectural object with physical properties and relationships to other components.

I modeled the building from the:

FoundationFirst FloorSecond FloorRoof

and added the major architectural components required to create the complete residence.

4. What BIM Added to the Project

One of the most important things I learned was the difference between CAD drafting and Building Information Modeling (BIM).

Traditional CAD is extremely useful for creating technical drawings.

BIM goes further because the project becomes a coordinated digital representation of the building.

That means architectural and electrical components exist within the same spatial environment.

For example, a receptacle isn't just a symbol floating on a drawing.

Within the BIM workflow, its location relates to an actual:

roomwallfloorbuilding

Likewise, electrical equipment has to coexist with walls, doors, furniture, plumbing spaces, stairs, and other building elements.

That relationship became especially important once I started the electrical portion of the project.

5. 3D Residential Modeling

I developed the house into a complete 3D residential model rather than only producing floor plans.

The model included the building's major architectural elements as well as furniture, materials, and finishes.

Adding these elements helped me understand how the building worked spatially instead of seeing it exclusively from a plan view.

It also helped me evaluate electrical-device placement from a more realistic perspective.

For example, when determining where a receptacle, switch, or lighting fixture should be located, the architectural model provides context about:

walls, doors, room usage, furniture, circulation paths, and available space.

That is one of the major advantages I found in working with BIM.

6. Residential Electrical Design

After developing the architectural model, I expanded the project into the electrical system.

I created electrical lighting and power plans for both floors of the residence.

The drawings show several different types of electrical devices, including:

Lighting

  • Ceiling-mounted fixtures
  • Recessed/pot lights
  • Pendant fixtures
  • Wall-mounted sconces

Controls

  • Single-pole switches
  • 3-way switches
  • Switch/control relationships

Power

  • Standard 120 V duplex receptacles
  • GFCI receptacles
  • Floor receptacles
  • 220 V receptacles
  • Electrical panel

Safety

  • Smoke detectors
  • Carbon-monoxide alarms

This required thinking about what each room actually needed rather than simply placing electrical symbols evenly throughout the house.

7. Lighting Layout

The lighting design was developed according to the purpose and geometry of each space.

Different spaces naturally require different lighting approaches.

For example, a kitchen, bathroom, bedroom, hallway, garage, and living area do not necessarily need identical fixture arrangements.

The project therefore used several fixture types rather than treating the entire house the same way.

I also developed the switching relationships between lighting fixtures and their controls.

The dashed control lines shown throughout the electrical plans document which switches operate particular lighting fixtures.

This is an important distinction:

A light fixture and a switch can both exist on a floor plan, but unless their control relationship is communicated, the drawing does not clearly explain how the lighting system operates.

8. Single-Pole vs. 3-Way Switching

The project also incorporated both single-pole and 3-way switches.

A single-pole switch provides control of a lighting load from one location.

A 3-way switching arrangement allows the same lighting load to be controlled from two different locations.

That becomes useful in spaces where a person may enter and leave from different directions, such as stairs, hallways, or rooms with multiple access points.

This made the electrical layout partly an electrical problem and partly a human-use problem:

Where would someone naturally expect to control this light?

That is something I became much more aware of while developing the plans.

9. Receptacle & Power Layout

I also developed the residential power layout by placing receptacles throughout the building according to the function of each space.

The design distinguishes between standard duplex receptacles and specialized receptacles such as GFCI-protected locations and higher-voltage outlets.

My project notes identify GFCI locations in areas such as kitchens, bathrooms, laundry/exterior areas, and locations close to sinks.

The purpose of differentiating these devices was to recognize that electrical requirements change depending on the environment in which the equipment operates.

Rather than viewing every outlet as identical, I began thinking about:

locationexpected load/useenvironmental conditionsappropriate electrical device

10. Electrical Safety Devices

The design also incorporated smoke detectors and carbon-monoxide alarms.

These devices were integrated into the residential plans alongside the lighting and power equipment.

My drawing notes identify smoke-detector placement in bedrooms, outside bedrooms, and on each storey, with carbon-monoxide alarms provided outside sleeping areas based on the residential guidance I was following.

This reinforced an important idea for me:

Electrical design isn't only about delivering power. It also includes designing systems that contribute to the safe operation and occupancy of the building.

11. Branch Circuits

One of the biggest steps beyond basic architectural BIM was organizing electrical loads into branch circuits.

A branch circuit is essentially the part of the electrical distribution system that carries power from the electrical panel to the connected electrical loads.

Conceptually:

Utility / ServiceMain Electrical PanelBranch CircuitElectrical Loads

The loads could include lighting, receptacles, or other electrical equipment.

Instead of treating every device as an isolated component, I began organizing devices according to the electrical circuit supplying them.

That is why circuit identifiers such as CKT-3, CKT-4, CKT-9, CKT-11, CKT-12, CKT-13, etc., appear throughout my plans.

This made the design more representative of an actual electrical distribution system rather than simply an architectural drawing with electrical symbols added on top.

12. Electrical Panel & Distribution

The electrical panel acts as the central distribution point for the branch circuits within the house.

At a simplified level, the power-distribution structure I was documenting was:

Incoming Electrical ServiceMain Electrical PanelCircuit Protection / Branch CircuitsLighting / Receptacles / Equipment

The panel therefore connects the building's incoming electrical supply to the individual circuits supplying the loads throughout the residence.

I used this understanding to organize circuit assignments and develop the electrical documentation.

13. Panel Schedule

I also developed a panel schedule as part of the project.

The floor plan tells someone where the electrical devices are physically located.

The panel schedule serves a different purpose: it organizes the electrical circuits associated with the distribution panel.

This allowed me to document the relationship between:

PanelCircuit NumberConnected Loads

Working through this process helped me understand that electrical drawings need both spatial information and electrical-distribution information.

14. Basic Load Calculations

I performed basic residential load calculations to support the electrical design.

The basic idea behind a load calculation is determining the electrical demand associated with the connected equipment.

For an individual load, electrical power can be understood through:

P = VI

where:

  • P = electrical power in watts
  • V = voltage
  • I = current

If power and voltage are known, current can be estimated through:

I=\frac{P}{V}

At the project level, load calculations help organize and understand how the different electrical loads relate to the building's distribution system.

15. Simplified Single-Line Diagram

I also developed a simplified single-line diagram representing the electrical distribution system.

A floor plan answers:

Where is everything?

A single-line diagram answers:

How is electrical power distributed through the system?

Instead of drawing every conductor individually, a single-line diagram simplifies the electrical network so that the relationship between the service, panel, circuits, and loads can be understood more easily.

Conceptually, mine represented:

Electrical ServiceMain PanelBranch CircuitsBuilding Loads

This gave me experience thinking about the house as an electrical system, rather than just a collection of electrical symbols placed on architectural drawings.

16. BIM / MEP Coordination

One of the most valuable parts of the project was learning about BIM/MEP coordination.

MEP stands for:

Mechanical, Electrical, and Plumbing.

In a real building, these systems all have to occupy the same physical space as the architecture and structure.

Electrical equipment therefore cannot simply be placed wherever it is most convenient on a drawing.

Its location needs to be considered relative to architectural features and available space.

Using the architectural model as the foundation of the electrical design allowed me to evaluate device locations, spatial clearances, and possible conflicts between the electrical layout and architectural elements.

That gave me an introductory understanding of the coordination process used on larger building projects.

17. Design Standards & Code Awareness

Throughout the project, I used Ontario Building Code guidance and accepted drafting practices to inform my work.

That distinction actually makes the project more credible.

The purpose was to develop experience working within the mindset of engineering and construction standards:

Don't just ask “Can I put this here?”

Ask:

“What requirements, clearances, conventions, safety considerations, and documentation standards affect where this should go?”

18. Independent Learning & Troubleshooting

This project was primarily self-directed, which meant that when I encountered something I did not know how to do in AutoCAD or Revit, I had to research it, understand the workflow, test it, identify mistakes, and revise the model.

The process was often:

AttemptProblemResearchTroubleshootModifyVerifyContinue

Because the project lasted from June 2025 to July 2026, I was able to progressively expand its scope rather than treating it as a one-time assignment.

What began primarily as architectural drafting eventually developed into a much broader project involving:

AutoCAD + Revit + BIM + residential electrical design + electrical documentation + coordination.

19. Complete Project Workflow

Architectural Concept2D AutoCAD Floor PlansDimensioned Drawing Package3D Revit Architectural ModelMaterials + Furniture + Building ComponentsElectrical Lighting LayoutSwitching + Receptacle LayoutElectrical Panel + Branch CircuitsBasic Load Calculations + Panel ScheduleSimplified Single-Line DiagramBIM/MEP Coordination + Design Review

That communicates the scale of the project much better than simply writing “Designed a house in AutoCAD and Revit.”

What This Project Demonstrates

Electrical Design: residential lighting, receptacles, switching, circuit assignments, panel connections, basic load calculations, and distribution-system documentation.

BIM: integrating electrical systems within a complete 3D architectural model.

CAD: creating organized, dimensioned 2D residential drawings.

Coordination: considering how electrical equipment interacts spatially with architectural elements.

Independent Engineering Development: teaching yourself new workflows, troubleshooting problems, and iterating over a long-term personal project.