I8 Interior Finishes: Project Management Internship project cover

I8 Interior Finishes: Project Management Internship

Hybrid · May 2026 – August 2026

Supported scheduling, trade coordination, CAD/BIM drawings, material takeoffs, and site documentation across commercial and residential interior projects, including a 16-room hotel floor completed in 12 days against a 14-day plan.

  • Project coordination
  • Scheduling
  • CAD/BIM
  • Procurement
  • Excel/VBA
16 roomsSandman Hotel floor renovation
12 dayscompletion against a 14-day plan
4 layoutsUpperVista sliding-door designs
16 rooms / 14 daysplanned scope and schedule

Internship Overview

During my internship with I8 Interior Finishes, I worked across multiple commercial and residential interior construction projects, supporting the planning, coordination, documentation, and execution of work from the office and on active job sites.

The experience showed me that project management in construction is much more than creating a schedule. Every project involved coordinating people, materials, drawings, manufacturers, site conditions, and deadlines at the same time.

My responsibilities exposed me to several parts of the project lifecycle:

Site ConditionsScope ReviewPlanningSchedulingDrawings & MeasurementsMaterial Quantities/ProcurementTrade CoordinationInstallationProgress TrackingHandover

Rather than working on one isolated task throughout the summer, I supported different projects and problems as they moved through different stages of construction.

Project Scheduling & Trade Coordination

One of my primary responsibilities was supporting project scheduling and site coordination.

Interior construction requires multiple trades to complete their work in the correct sequence. Demolition may need to finish before drywall begins; drywall needs to be completed and prepared before certain finishes can be installed; electrical work may need to occur before areas are closed or finished.

This means that scheduling isn't simply:

“Trade A works Monday and Trade B works Tuesday.”

The important question is:

What work has to be completed before the next trade can begin, and what happens to the rest of the schedule if that work is delayed?

I worked with labourers, subcontractors, and trade contractors to coordinate these dependencies while projects were operating under tight schedules.

This gave me practical experience with the difference between a planned schedule and what actually happens on a construction site.

Weather, material availability, unfinished predecessor work, access, labour availability, and unexpected site conditions can all change the plan.

My role required monitoring those changes and helping adjust the sequence of work rather than simply following the original schedule.

Sandman Hotel — Schedule Management

One of the strongest examples was the 16th-floor renovation at the Sandman Hotel.

The floor consisted of 16 rooms undergoing renovation, with several trades needing access to the same spaces during different stages of the project.

I developed a 14-day trade schedule coordinating activities including demolition, drywall work, sanding, priming, wallpaper installation, and other finishing activities.

The challenge was not simply fitting tasks into fourteen days.

The trades had dependencies.

For example:

DemolitionWall preparation/drywallSandingPrimingFinishing/Wallpaper

If an earlier activity slipped, the delay could propagate into the trades scheduled afterward.

That required looking at the schedule as a connected sequence of dependencies rather than independent appointments.

Responding to Schedule Changes

Construction rarely follows the first schedule perfectly.

When delays or conflicts occurred, I had to consider what work could still continue, which activities depended on the delayed task, and whether other trades could be moved forward without creating interference.

That taught me an important project-management principle:

A schedule isn't useful because it predicts everything perfectly. It is useful because it gives a project team a framework for responding when reality changes.

Through coordination and schedule management, the 16-room floor was ultimately completed in 12 days against the planned 14-day schedule.

UpperVista — Custom Sliding Glass Door System

Another major part of my internship involved technical design and coordination for UpperVista residential condominium units.

This work required me to combine site measurements, drawings, CAD/BIM modeling, material considerations, and manufacturer/installation requirements.

I worked across four different layouts, taking measurements and developing designs for custom sliding-glass-door assemblies.

Understanding the Sliding-Door System

The assembly consisted of large tempered-glass panels supported within a metal-framed sliding-track system.

The drawings document major components including:

12 mm tempered glassmetal framingvertical corner mulliontop trackbottom trackrollers/soft-close hardwareguides/stopshandles

The system was arranged around a corner, so the design had to account for two intersecting runs rather than one simple straight sliding door.

The drawings show nominal runs of approximately:

1600 mm on one side and 2400 mm on the adjoining side

with an overall height of approximately:

2700 mm.

The system therefore had to be considered in three dimensions.

Why the Corner Was Important

A standard straight sliding door primarily operates along one direction.

This design met at a 90-degree corner, introducing an additional coordination point.

The corner mullion had to establish the transition between the two glazed runs while the tracks, panels, frame, and surrounding construction remained properly aligned.

Conceptually:

Wall/StructureTrack systemSliding glass panelsCorner mullionPerpendicular glass system

If the corner geometry or dimensions were incorrect, the error could affect the fit of both sides.

That made accurate field measurements and clear technical documentation especially important.

Technical Drawing Package

The drawings communicate the design through several different views because no single view contains enough information to completely describe the system.

Front Elevation

The elevation communicates the overall appearance and vertical dimensions of the assembly.

It shows the 2700 mm height, the two primary horizontal spans, panel divisions, framing, handles, and intended sliding directions.

Plan View

The top view communicates something the elevation cannot clearly show:

how the two door systems meet at the corner.

It documents the relationship between the tracks, surrounding walls, interior/exterior orientation, and panel movement.

Vertical Section

The vertical section cuts through the assembly to show how the system works from floor to ceiling.

It identifies:

Structure/CeilingTop TrackGlass/FrameBottom TrackFinished Floor

This view is particularly important because the appearance of the door alone doesn't explain how it is physically supported and guided.

Horizontal Corner Section

The horizontal section shows the detailed relationship between the two sliding assemblies and the vertical corner mullion.

It communicates the track configuration and how the perpendicular glass panels meet at the corner.

Together:

Elevation = what it looks like
Plan = how it is arranged
Vertical section = how it connects floor-to-ceiling
Horizontal section = how the corner and tracks interface

That is exactly why construction drawing sets use multiple views.

From Site Measurement to Fabrication Information

One of the most useful things I learned from this work was that a field measurement has to eventually become usable information for somebody else.

The process was approximately:

Site ConditionField MeasurementsInterpret GeometryDevelop CAD/BIM ModelDimension & Detail AssemblyCoordinate Components/MaterialsCommunicate with Manufacturer/InstallerFabrication & Installation

A mistake early in that chain can become much more expensive later.

For example, an incorrect opening dimension could result in a fabricated panel or track not fitting the actual site.

That made measurement accuracy and drawing clarity much more meaningful than they had been when I only used CAD academically.

Material & Hardware Considerations

The drawing package also documents the intended material and hardware system.

The design called for 12 mm tempered clear glass, metal framing with a matte-black finish, sliding tracks, a corner mullion, pull handles, rollers/soft-close hardware, and floor guides/stops.

The notes also required field dimensions to be verified before fabrication.

That last point is important.

Construction drawings communicate design intent, but actual site conditions have to be verified before custom components are manufactured.

This project helped me understand why technical drawings contain notes such as:

“Contractor to verify all dimensions on site prior to fabrication and installation.”

It protects against assuming that the built environment perfectly matches an earlier drawing or measurement.

Moxies Hamilton — Material Takeoffs & Procurement

Another area I worked in was material quantity calculation and procurement support for Moxies Hamilton.

I worked from project drawings and site information to determine quantities for materials such as:

LVT flooring, tile, upholstery, and architectural finishes.

This introduced me to the practical purpose of a material takeoff.

A drawing communicates what needs to be built.

A takeoff begins converting that design into:

How much material do we actually need to order?

Conceptually:

Drawing dimensionsareas/quantitiesmaterial requirementsprocurement

The quantity needs to be accurate enough to avoid two opposite problems.

Under-ordering can stop work because the crew runs out of material.

Over-ordering creates unnecessary cost and waste.

That helped me understand how engineering drawings connect directly to cost, purchasing, logistics, and schedule performance.

Manufacturer & Supplier Coordination

The internship also exposed me to the relationship between the design team, site team, suppliers, and manufacturers.

For custom components, the information communicated to a manufacturer needs to be clear enough for them to understand what is actually required.

That can include:

dimensions, quantity, material, finish, configuration, installation constraints, and schedule requirements.

This gave me experience thinking about drawings not as something created just to satisfy a design requirement, but as a communication interface between different people responsible for delivering the project.

Electrical Site Scope

I also gained exposure to electrical work as part of the broader interior construction scope.

This included supporting work involving fixture removal and new lighting, along with installation/testing associated with 24 exterior patio fixtures.

This experience was valuable because I was able to see electrical work within the context of an actual construction project.

A lighting fixture isn't installed in isolation.

Its installation may depend on:

site accessexisting conditionselectrical connectionsmountingsurrounding finishessafetytestingschedule

That helped connect the electrical concepts I was learning academically with how electrical scope interacts with other trades in the field.

Site Documentation Problem

Another problem I noticed during the internship was the way project progress was being documented.

Construction projects generate a huge number of photos.

Those photos may show:

completed work, deficiencies, existing conditions, deliveries, trade progress, hidden work, or damage.

But a photo isn't particularly useful if nobody can determine:

Where was this taken? When was it taken? Which contractor/trade does it relate to? What am I supposed to notice?

I recognized an opportunity to improve that workflow.

GPS-Based Documentation Concept

I developed the concept for a more organized site-documentation workflow using information such as:

timestamp/location information + contractor/trade identification + progress photos + voice notes + categorized records.

The objective was to make site documentation easier to retrieve and understand instead of allowing important project information to remain scattered across individual phones and photo galleries.

The idea followed:

CaptureIdentifyTagOrganizeRetrieve

rather than:

Take photoleave it in camera rolltry to find it weeks later.

This was one of the parts of the internship that most directly involved process improvement rather than simply carrying out an existing workflow.

Excel/VBA Time-Tracking Automation

I also identified an opportunity to improve employee time tracking.

Rather than relying entirely on manual recording, I developed an Excel/VBA employee-ID clock-in system that could be used through an iPad-based workflow.

At a high level:

Employee enters/selects IDsystem records clock-in informationdata stored consistentlyrecords available for tracking

The important part wasn't simply writing VBA.

It was recognizing a repetitive administrative process and asking:

Can I make this faster and more consistent using a simple technical solution?

This gave me practical experience using programming/automation outside of a traditional software project.

Project Management as a System

One of the biggest things I took away from the internship was that project management is really a systems problem.

A construction project has several connected variables:

Scope

What needs to be built?

↓

Drawings

How should it be built?

↓

Materials

What needs to be purchased?

↓

People/Trades

Who performs the work?

↓

Schedule

When can each activity happen?

↓

Site Conditions

What is actually happening in the field?

↓

Documentation

How do we know what has been completed?

↓

Handover

Is the project actually ready to deliver?

A change in one area can affect several others.

A late material delivery can affect a trade.
A delayed trade can affect the schedule.
A dimensional problem can affect fabrication.
A fabrication problem can affect installation.
An installation delay can affect finishing trades.

That interdependence was probably the most important thing I learned during the internship.

Balancing Office and Field Work

Because the internship was hybrid, I was able to see both sides of project delivery.

In the office/design environment, I worked with:

drawings, schedules, quantities, CAD/BIM, documentation, procurement information, and process improvement.

On site, those documents became:

workers, materials, rooms, equipment, installations, delays, measurements, and physical constraints.

Seeing both sides helped me understand why something that appears simple on a drawing can become complicated during installation.

It also showed me why project managers need enough technical understanding to communicate with both designers and trades.

Complete Internship Workflow

Client / Project RequirementsSite Review & MeasurementsScope DevelopmentCAD/BIM DrawingsMaterial TakeoffsProcurement / Manufacturer CoordinationTrade SchedulingSite ExecutionProgress DocumentationTesting / DeficienciesProject Handover

What This Internship Demonstrates

Project Management: scheduling, sequencing, subcontractor/trade coordination, deadline management, progress tracking, and adapting plans when site conditions changed.

Technical Design: field measurements, CAD/BIM modeling, custom sliding-door layouts, construction drawings, sections, dimensions, and translating site conditions into technical documentation.

Project Controls & Procurement: material quantity calculations, takeoffs, manufacturer coordination, purchasing information, and understanding how material availability affects project schedules.

Process Improvement: identifying inefficient workflows and developing solutions such as the GPS-based documentation concept and Excel/VBA employee time-tracking system.

What I Learned

The biggest difference between this internship and my university projects was that the consequences were real.

A wrong dimension could affect fabrication.

A missed material quantity could affect procurement.

A scheduling mistake could leave a trade unable to work.

Poor documentation could make it difficult to determine what happened on site.

And a delay in one activity could affect several activities after it.

The internship taught me to think beyond completing my own individual task and instead consider:

How does my work affect the people and tasks that come after me?

It strengthened my ability to communicate technical information, coordinate multiple responsibilities, solve problems under time constraints, and connect engineering/design work with actual project execution.